Industrial
Industrial Production Facility
Steel structures, industrial floors and utilities, with production equipment installed during construction.
- Client type
- Industrial group
- Location
- Dammam
- Year
- 2024
- Area
- 9,600 m²
- Duration
- 14 months
- Role
- General contractor
The brief
An expansion of a live facility with a new production line. The client required the existing line to keep running while new equipment was installed alongside building works.
The constraint
Working inside a live plant imposed limits on noise, dust and power, and any unplanned outage cost production. Equipment slabs also needed curing time that did not fit the overall schedule.
The decision
We isolated the expansion behind an independent temporary wall, cast equipment slabs first with an accelerated curing plan, then erected the frame around the line route. Electrical tie-ins were scheduled into short, pre-agreed shutdown windows.