Residential
Al Waha Residential Compound
84 homes and shared amenities, handed over in three phases with early occupancy for the first block.
- Client type
- Property developer
- Location
- Riyadh
- Year
- 2023
- Area
- 18,400 m²
- Duration
- 24 months
- Role
- General contractor
The brief
We were asked to deliver an 84-home compound on uneven ground, with the first block handed over before the school term so the developer could occupy it and sell the remainder.
The constraint
Early handover meant working on three fronts at once while connecting utilities still under construction. Any structural delay in block one would have delayed the whole sale.
The decision
We split the site into three independent zones, front-loaded foundations and frames for block one, then moved crews to its finishes while block two started. A fixed weekly pour date kept concrete moving, and temporary service corridors kept works running.